CalcuForge
Real Estate & Civil

Concrete Mix & Volume Estimator

Enter your slab or footing dimensions and concrete grade to get cement bags, sand, and aggregate quantities.

Slabs are typically 100–200mm. Footings vary by design load.

Covers spillage and over-excavation. 5% is a common allowance.

Cement required
127bags (50kg)
Sand required
10,584kg
Aggregate required
19,184kg
Full material breakdown
QuantityValue
Wet (compacted) volume15.75 m³
Dry volume (× 1.54 bulking)24.255 m³
Cement127 bags · 6,350 kg
Sand6.615 m³ · 10,584 kg
Aggregate13.23 m³ · 19,184 kg
Water (approx., w/c 0.5)3,175 liters
Formula

How material quantities are derived

Dry volume = L × W × T × 1.54
Material = Dry volume × (ratio part ÷ sum of ratio)
L, W, TLength, width, and thickness of the pour, converted to meters
1.54Standard dry-volume (bulking) factor for loose ingredients
RatioCement : sand : aggregate for the selected grade, e.g. 1 : 1.5 : 3
Cement bagsCement weight (kg) ÷ 50kg per standard bag
Worked example

A 10m × 10m slab, 150mm thick, M20

With 5% wastage, the wet volume is 10 × 10 × 0.15 × 1.05 ≈ 15.75 m³. Multiplying by the 1.54 bulking factor gives a dry volume of about 24.26 m³. Splitting that across the M20 ratio (1 : 1.5 : 3, five and a half parts total) works out to roughly 127 bags of cement, 10,580 kg of sand, and 19,180 kg of aggregate.

MaterialQuantity
Cement≈ 127 bags
Sand≈ 10,580 kg
Aggregate≈ 19,180 kg
Comparison

Choosing a concrete grade

The grade sets the cement-to-aggregate ratio, which sets both strength and cost. Richer mixes (more cement relative to aggregate) cost more per cubic meter but carry more load — matching the grade to the actual job avoids over- or under-specifying.

GradeRatio (C:S:A)Typical use
M101 : 3 : 6Plain concrete — leveling course, blinding layer
M151 : 2 : 4Light footings, non-structural work
M201 : 1.5 : 3RCC slabs, beams — most residential work
M251 : 1 : 2Heavier structural elements, higher-load columns
FAQ

Common questions

Wet (compacted) volume is how much finished concrete you end up with. But loose dry ingredients — cement powder, sand, and aggregate — contain air gaps between particles that disappear once mixed and compacted. A dry volume factor of 1.54 (a 54% increase) is the standard rule-of-thumb correction used across nominal-mix estimating.

Related tools